Location: | Abu Dhabi, UAE |
Client: | ADNOC Sour Gas (Al Hosn Gas) |
Main Contractor: | CCC / CCEL Consortium |
EPC Work | US$ 50 Million |
Year Awarded | 2014 |
Completion Date | 2015 |
Project Period | 18 months |
Details
Installation of Gas Pads with four (4) Gas Wells per pad and associated flow lines with each of capacity 50 MMSCFD.