Location: Abu Dhabi, UAE
Client: ADNOC Sour Gas (Al Hosn Gas)
Main Contractor: CCEL part of CCC Group
EPC Work US$ 550 Million
Year Awarded 2011
Completion Date 2015
Project Period 40 months

Details

Shah Sulphur Station & Pipelines project within Shah Gas Development Program (SGDP), EPC Package 11 for dual 11 km pipeline, storage of liquid sulphur, blocking, granulation, railcar loading, and storage of elemental granular sulphur, conveyor and stacker/reclaimer systems, utilities, and infrastructure facilities.