Location: | Abu Dhabi, UAE |
Client: | ADNOC Sour Gas (Al Hosn Gas) |
Main Contractor: | CCEL part of CCC Group |
EPC Work | US$ 550 Million |
Year Awarded | 2011 |
Completion Date | 2015 |
Project Period | 40 months |
Details
Shah Sulphur Station & Pipelines project within Shah Gas Development Program (SGDP), EPC Package 11 for dual 11 km pipeline, storage of liquid sulphur, blocking, granulation, railcar loading, and storage of elemental granular sulphur, conveyor and stacker/reclaimer systems, utilities, and infrastructure facilities.