Location: | Abu Dhabi, UAE |
Client: | ADNOC Gas Processing (GASCO) |
Main Contractor: | CCEL part of CCC Group |
EPC Work | US$ 290 Million |
Year Awarded | 2006 |
Completion Date | 2010 |
Project Period | 30 months |
Details
Onshore Pipeline & Habshan Facilities:
Pipeline works 30” & 12”; Process & Utilities: Installation of Air coolers, HP Separators, MP Separators, feed pre Heaters, Vapor Re compressor, Stabilizer, Debutanizer& Other Equipment (Pumps etc.); Common equipment (Installation of Metering Package, Scupper, Pumps & Cranes); Installation of Electrical Works & Instrumentation Systems.